• SCOPE OF WORK

    Design, procurement, fabrication, testing, delivery, installation, and commissioning

  • VALUE

    $730 million

  • SCHEDULE

    2011–2019+

  • BUSINESS

    Nuclear, Security & Environmental

Safely decommissioning a 1950s nuclear waste storage facility

The UK government is undertaking the challenging job of cleaning up decades' worth of accumulated waste from nuclear research and production. A Bechtel joint venture partnered with the UK to perform critical nuclear-waste work at the Sellafield nuclear site in northwest England, all aimed at improving the environment for future generations.

The Pile Fuel Cladding Silo is a six-story structure with chambers that hold radioactive waste and other debris. It's known as one of Europe's most hazardous buildings. Bechtel Cavendish Nuclear Solutions designed, fabricated, installed, and commissioned silo doors and remote-operated waste retrieval and handling modules for the Pile Fuel Cladding Silo Retrieval project under contract to Sellafield Ltd. The project is part of a UK Nuclear Decommissioning Authority program to decommission nuclear storage facilities dating to the early 1950s.

The ultimate goal is to deliver a system that will allow Sellafield to retrieve the waste, package it safely, and dispose of it permanently. 

 

 

 

Widget Image

Three phases of the project

  1. Mobilization and project familiarization
  2. Completing design, specifications, procurement packages, and safety-case support
  3. Procurement, manufacture, works testing, construction, installation, and commissioning

Inside the project

Commissioned for use in 1952, the Pile Fuel Cladding Silo received and safely stored radioactive cladding―pieces of metal tubes—used for uranium fuel rods in some of the UK's earliest nuclear reactors―first from military projects and later power plants. Other debris was added, and by 1964 the silo was full.

  • The Pile Fuel Cladding Silo is 69 feet (21 meters) tall and houses six compartments that hold some 4,200 cubic yards (more than 3,200 cubic meters) of intermediate-level waste.
  • Upgrade work completed in the 1990s made it possible for this silo and other structures to continue storing waste safely.
  • The job at hand is safely retrieving the waste and storing it in highly secure concrete containers.